- Pillar 1: Substrate Integrity and Profile. The foundation is everything. We don’t just clean the concrete bond beam; we mechanically profile it. I mandate a surface profile equivalent to an ICRI CSP-3 (International Concrete Repair Institute, Concrete Surface Profile). This is achieved with a diamond grinder, creating a rough, porous surface for a tenacious mechanical bond. We then ensure the substrate is completely free of curing compounds, dust, and laitance.
- Pillar 2: The Uncoupling & Waterproofing Membrane. This is the step most installers skip to save costs, and it's a fatal mistake. I apply a liquid-applied, crack-isolation waterproofing membrane over the prepared concrete. This serves two functions: it prevents any moisture from the pool shell or ground from migrating up and attacking the thin-set from below, and it provides an uncoupling layer that absorbs minor substrate movement.
- Pillar 3: The Adhesive and Grout Specification. We never use standard mortar. My specification calls for a high-performance, polymer-modified thin-set mortar meeting ANSI A118.15 standards. This type of mortar has superior bond strength and, crucially, high flexibility. For grout, I forbid the use of standard cementitious grout. We exclusively use a 100% solids epoxy grout for its non-porous nature, chemical resistance (chlorine, salt), and stain-proof qualities.
- Step 1: Substrate Grinding and Cleaning. Mechanically abrade the entire concrete surface where the coping will be installed. Vacuum all dust and wipe with a damp sponge to remove any residual fine particles. The surface must be perfectly clean.
- Step 2: Membrane Application. Apply the liquid waterproofing and crack-isolation membrane according to the manufacturer's specifications, ensuring you achieve the required dry film thickness (DFT). Allow it to cure completely.
- Step 3: Mortar Mixing and Directional Troweling. Mix the ANSI A118.15 mortar to a smooth, lump-free consistency. Using a 1/2" x 1/2" square-notched trowel, apply the mortar to the cured membrane, combing the ridges in a single direction, perpendicular to the long edge of the coping.
- Step 4: Back-Buttering for 100% Coverage. This is non-negotiable. Apply a thin, flat coat of mortar to the entire back of each piece of porcelain coping. This ensures we achieve 100% mortar coverage, eliminating any hollow spots that could collect water and fail during a freeze-thaw cycle.
- Step 5: Setting and Curing. Firmly press each piece of coping into the mortar with a slight twisting motion to collapse the trowel ridges. Use 3/16" tile spacers to maintain consistent grout joints. The installation must be protected from rain and direct sun for at least 72 hours to allow the mortar to cure properly.